NEW QUESTION # 222
Which is a minimum requirement for applying the change theme?

  • A. To produce a breakdown of the products to be produced
  • B. To identify whether an issue affects the continuation of the project
  • C. To ensure each change is managed as an exception
  • D. To tailor all changes to improve the quality of the project

Answer: B

Explanation:
A minimum requirement for applying the change theme in PRINCE2 is to identify whether an issue has the potential to affect the continuation of the project. This involves assessing the impact of potential changes or issues on the project's objectives and deciding whether they warrant considering the project as unviable in its current form.References: = PRINCE2 7 Foundation handbook and online resources


NEW QUESTION # 223
How should the Team Manager report that tolerances are forecast to be exceeded?

  • A. Raise an issue
  • B. Grant a concession
  • C. Create a Highlight Report
  • D. Create an Exception Report

Answer: A


NEW QUESTION # 224
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

  • A. Write an Exception Report
  • B. Raise a request for change
  • C. Raise an off-specification
  • D. Amend the Work Package

Answer: C


NEW QUESTION # 225
What is an off-specification?

  • A. A quality tolerance
  • B. A new requirement
  • C. A major risk
  • D. A type of issue

Answer: D


NEW QUESTION # 226
What is a purpose of the 'quality' practice?

  • A. To resolve off-specifications, that are Identified during the project, at the end of the project
  • B. To plan the project so that there is time to deal with quality defects late in the project
  • C. To identify the user's expectations and determine how the project will achieve them
  • D. To predict whether the project will deliver on time and to cost and whether the benefits will outweigh the costs

Answer: B

Explanation:
The project manager needs to prioritize several criteria that the project product must meet for acceptance during the step of 'Describing the quality management approach'. This step involves defining how quality will be managed throughout the project, ensuring that all quality criteria are clearly identified, prioritized, and agreed upon by stakeholders. References: PRINCE2 Foundation manual and quality management technique guidelines.


NEW QUESTION # 227
Which is a purpose of the Initiating a Project process?

  • A. Establish solid foundations for a project
  • B. Identify the number of Work Packages required
  • C. Decide if it is worthwhile to initiate a project
  • D. Decide on the project approach

Answer: A


NEW QUESTION # 228
The application of which principle helps to define what should be included in a project?

  • A. Defined roles and responsibilities
  • B. Continued business justification
  • C. Focus on products
  • D. Manage by stages

Answer: D


NEW QUESTION # 229
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

  • A. Both parties must apply the same external governance to the project
  • B. Each party may have their own business case for undertaking the project
  • C. Management systems need to be unified for successful project delivery
  • D. The risk appetite should be collaboratively set before the project starts

Answer: B

Explanation:
Section: Volume B


NEW QUESTION # 230
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. controls
  • B. products
  • C. stages
  • D. project management team

Answer: B


NEW QUESTION # 231
Which is a typical core activity within configuration management?

  • A. Identification
  • B. Quality inspection
  • C. Issue management
  • D. Preparation

Answer: A


NEW QUESTION # 232
Which describes an off-specification?

  • A. An interdependency between products that was previously unidentified
  • B. The addition of an improvement to a product description
  • C. The production of more than the defined quantity of a specialist product
  • D. A prototype demonstrating a possible design solution

Answer: A

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-change-control/


NEW QUESTION # 233
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4

Answer: B

Explanation:
Explanation
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2


NEW QUESTION # 234
Which risk response is applied on a pain/gain basis?

  • A. Accept
  • B. Share
  • C. Enhance
  • D. Exploit

Answer: B

Explanation:
Reference https://www.prince2primer.com/prince2-2017-risk-responses-and-planning/


NEW QUESTION # 235
Which is an objective of the 'managing a product delivery' process?

  • A. To request authorization to start the next stage
  • B. To ensure the business case is regularly reviewed
  • C. To deliver the planned specialist products within tolerance
  • D. To assess whether the stage products have been approved

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Managing_Product_Delivery#Objective


NEW QUESTION # 236
Which risk response type is appropriate to respond to an opportunity?

  • A. Accept
  • B. Fallback
  • C. Exploit
  • D. Transfer

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 237
Which describes a risk event?

  • A. The achievement of a milestone on the project plan
  • B. The derivation or sources of a potential risk to the project
  • C. The area of uncertainty in terms of the threat or opportunity
  • D. The sequence of events and actions that will be put in place if a risk occurs

Answer: C

Explanation:
A risk event in PRINCE2 is described as the area of uncertainty in terms of the threat or opportunity. It specifically refers to a specific set of circumstances that may occur and impact the project if the risk materializes. This description encapsulates the nature of a risk as being either a potential threat or an opportunity based on uncertain events that might affect project objectives.
PRINCE2 7 Foundation handbook and official documents.


NEW QUESTION # 238
Which is a purpose of the Risk theme?

  • A. Establish a cost-effective procedure to identify, assess and control uncertainty
  • B. Establish mechanisms to control any unacceptable deviations from plan
  • C. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  • D. Establish mechanisms to manage risks at the corporate or programme level of an organization

Answer: A


NEW QUESTION # 239
......


The PRINCE2 Foundation certification exam consists of 60 multiple-choice questions, and the duration of the exam is 60 minutes. The passing score is 55%, which means that the candidate needs to answer at least 33 questions correctly out of 60. PR2F exam is available in several languages, and the certification is valid for three years. Candidates who pass the PRINCE2 Foundation exam can move on to the next level of certification, which is the PRINCE2 Practitioner certification.

 

Latest EXIN PR2F Practice Test Questions: https://www.examsreviews.com/PR2F-pass4sure-exam-review.html

Realistic PR2F Accurate & Verified Answers As Experienced in the Actual Test!: https://drive.google.com/open?id=1IRibzVhPaD2OJzss4E19qR4l3bxMHXib