AACE International is a globally recognized professional association for cost engineering, project management, and planning and scheduling professionals. AACE International offers various certification programs to recognize professionals' expertise in different areas. AACE-PSP (Planning & Scheduling Professional) is one of the certification programs that AACE International offers.
NEW QUESTION # 18
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
- A. 30 lifts
- B. 48 lifts
- C. 36 lifts
- D. 24 lifts
Answer: C
NEW QUESTION # 19
Under which circumstance should one perform resource-leveling calculations?
- A. When you believe that known resource limitations may override schedule logic.
- B. When the contract contains a provision for float-banking.
- C. Never, unless required by the contract.
- D. When the schedule is resource-loaded.
Answer: A
NEW QUESTION # 20
What is the workweek period for this project?
- A. Sunday through Friday
- B. Monday through Saturday
- C. Sunday through Saturday
- D. Monday through Friday
Answer: C
NEW QUESTION # 21
Which of the following is NOT true?
- A. A network must contain only one Critical Path.
- B. Constraints can interfere with the longest path calculation.
- C. Multiple calendars can affect the total float calculation.
- D. Remaining durations can exceed original durations.
Answer: D
NEW QUESTION # 22
What activities are concurrent to Activity 2001 in the "normal" schedule?
- A. 7001.
- B. 2003.
- C. 1000.
- D. 1001.
Answer: A
NEW QUESTION # 23
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 255 days
- B. 407 days
- C. 267 days
- D. 362 days
Answer: B
NEW QUESTION # 24
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
- A. Excusable delay
- B. Non-excusable delay
- C. Compensable delay
- D. Non-compensable delay
Answer: D
NEW QUESTION # 25
Why does activity 11001 not show successor activities?
- A. It is the final activity for the required work for the project
- B. The scheduler forgot to add the successor activities
- C. It is the penultimate work required for the project
- D. The early finish and late finish are circular
Answer: A
NEW QUESTION # 26
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- B. The activities run concurrently.
- C. The activities occur in series with a 15-day lag.
- D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
Answer: C
NEW QUESTION # 27
Which statement is true?
- A. Where compensability can be established, excusabltity cannot be assumed.
- B. Where compensability cannot be established, excusability is a given.
- C. Where compensability can be established, excusability is assumed.
- D. Where compensability cannot be established, excusability is assumed.
Answer: D
NEW QUESTION # 28
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
- A. 02-19-04.
- B. LS.11001 + 25 days.
- C. EF.11001 + 1 day.
- D. EF.11001.
Answer: A
NEW QUESTION # 29
Constraints control events or activities that __________________.
- A. Affect only the backward pass.
- B. Affect only the forward pass.
- C. May be over-ridden by activity logic.
- D. Are not based on project relationships.
Answer: C
NEW QUESTION # 30
Which of the following will always describe the critical path? The path with
- A. Negative float.
- B. The longest duration through the network.
- C. Zero float.
- D. The shortest duration and negative float.
Answer: C
NEW QUESTION # 31
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2004.
- B. 4001 and 5001.
- C. 2003 and 7001.
- D. 4001, 5001 and 6001.
Answer: B
NEW QUESTION # 32
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. C.
- B. S.
- C. B.
- D. W.
Answer: B
NEW QUESTION # 33
Why does activity 1001 have two successor activities?
- A. Because the problem could not effectively work with only one successor
- B. Because there are two defined logic paths for the work
- C. Because the duration of activities 2001, 2002 and 200.f require two successors
- D. Because the late finish of 1001 and the late start of 7001 require two successors
Answer: B
NEW QUESTION # 34
Determine the driving activity for Activity 10001.
- A. There is no driving activity for Activity 10001 in the backward pass.
- B. Activity 9005.
- C. Activity 10002.
- D. Activity 11001.
Answer: C
NEW QUESTION # 35
......