NEW QUESTION 47
Which is a minimum requirement for applying the quality theme?
- A. To use user stories to inform the project product description
- B. To use lessons to inform quality planning
- C. To use external quality standards for quality control
- D. To use the prescribed approach to quality management
Answer: D
Explanation:
Explanation
Reference http://prince2.wiki/Quality
NEW QUESTION 48
Which is a minimum requirement for applying the quality theme?
- A. To use user stories to inform the project product description
- B. To use lessons to inform quality planning
- C. To use external quality standards for quality control
- D. To use the prescribed approach to quality management
Answer: D
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Quality
NEW QUESTION 49
Which is a true statement about time-driven controls?
- A. Time-driven controls are produced at the end of a stage
- B. An Exception Report is a time-driven control
- C. Time-driven controls take place when specific events happen
- D. Time-driven controls are used for monitoring the progress of Work Packages and management stages
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 50
What do customer's quality expectations identify?
- A. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
- B. Reviewer names for each product
- C. Skills required to develop the project product
- D. Standards that must be used in order to meet the level of quality needed
Answer: D
NEW QUESTION 51
How many roles make up the Project Board?
- A. Two
- B. Three
- C. One
- D. Four
Answer: B
NEW QUESTION 52
Which is a purpose of a Risk Register?
- A. Capture issues which are impacting on the delivery of the project objectives
- B. Capture risks that may occur during the project
- C. Record how risk management activities will be undertaken on the project
- D. Record the risk tolerance for the project
Answer: B
NEW QUESTION 53
What should be considered when defining the number of management stages in a project?
- A. When key decisions need to be made
- B. When the team managers are available
- C. When project support will be available
- D. When highlight reports will be submitted
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-management-and-technical-stages/
NEW QUESTION 54
What must a PRINCE2 project demonstrate?
- A. Application of PRINCE2 principles
- B. Application of proper leadership skills
- C. Application of the activities in each process
- D. Application of tools appropriate for the industry
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 55
Which is performed as part of the recommended risk management procedure?
- A. Resolution of conflicts between the project and the programme board
- B. Review of risk management practices to ensure that they are performed effectively
- C. Sending of information about risks to the project to project stakeholders
- D. Allocation of a budget to investigate issues facing the project
Answer: C
NEW QUESTION 56
Which activity takes place within the Managing a Stage Boundary process?
- A. Produce an Exception Plan
- B. Authorize a Stage Plan for the next stage
- C. Take corrective action within the limits of a stage's tolerance
- D. Produce Highlight Reports
Answer: A
NEW QUESTION 57
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
- A. Both 1 and 2 are true
- B. Neither 1 or 2 are true
- C. Only 2 is true
- D. Only 1 is true
Answer: A
NEW QUESTION 58
Which is a purpose of the Directing a Project process?
- A. Ensure that work on products allocated to the team is authorized and agreed
- B. Control the day-to-day running of the project
- C. Create and authorize the project mandate
- D. Delegate day-to-day management of the project to the Project Manager
Answer: D
NEW QUESTION 59
What must a PRINCE2 project demonstrate?
- A. Application of PRINCE2 principles
- B. Application of proper leadership skills
- C. Application of the activities in each process
- D. Application of tools appropriate for the industry
Answer: A
NEW QUESTION 60
How many tasks does the product-based planning technique describe?
- A. Two
- B. Three
- C. One
- D. Four
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 61
Which describes an off-specification?
- A. A prototype demonstrating a possible design solution
- B. The addition of an improvement to a product description
- C. An interdependency between products that was previously unidentified
- D. The production of more than the defined quantity of a specialist product
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/
NEW QUESTION 62
......