Pay attention to our Valid and Useful Exam Reviews and take our Exam Torrent as your Study Material. With little time and energy investment, you have a High Efficiency Study experience. Pass your Actual Test with the help of our Actual Reviews.

Verified PRINCE2Foundation dumps Q&As - 2022 Latest PRINCE2Foundation Download [Q47-Q62]

Share

Verified PRINCE2Foundation dumps Q&As - 2022 Latest PRINCE2Foundation Download

Dumps Questions [2022] Pass for PRINCE2Foundation Exam

NEW QUESTION 47
Which is a minimum requirement for applying the quality theme?

  • A. To use user stories to inform the project product description
  • B. To use lessons to inform quality planning
  • C. To use external quality standards for quality control
  • D. To use the prescribed approach to quality management

Answer: D

Explanation:
Explanation
Reference http://prince2.wiki/Quality

 

NEW QUESTION 48
Which is a minimum requirement for applying the quality theme?

  • A. To use user stories to inform the project product description
  • B. To use lessons to inform quality planning
  • C. To use external quality standards for quality control
  • D. To use the prescribed approach to quality management

Answer: D

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Quality

 

NEW QUESTION 49
Which is a true statement about time-driven controls?

  • A. Time-driven controls are produced at the end of a stage
  • B. An Exception Report is a time-driven control
  • C. Time-driven controls take place when specific events happen
  • D. Time-driven controls are used for monitoring the progress of Work Packages and management stages

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 50
What do customer's quality expectations identify?

  • A. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
  • B. Reviewer names for each product
  • C. Skills required to develop the project product
  • D. Standards that must be used in order to meet the level of quality needed

Answer: D

 

NEW QUESTION 51
How many roles make up the Project Board?

  • A. Two
  • B. Three
  • C. One
  • D. Four

Answer: B

 

NEW QUESTION 52
Which is a purpose of a Risk Register?

  • A. Capture issues which are impacting on the delivery of the project objectives
  • B. Capture risks that may occur during the project
  • C. Record how risk management activities will be undertaken on the project
  • D. Record the risk tolerance for the project

Answer: B

 

NEW QUESTION 53
What should be considered when defining the number of management stages in a project?

  • A. When key decisions need to be made
  • B. When the team managers are available
  • C. When project support will be available
  • D. When highlight reports will be submitted

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 54
What must a PRINCE2 project demonstrate?

  • A. Application of PRINCE2 principles
  • B. Application of proper leadership skills
  • C. Application of the activities in each process
  • D. Application of tools appropriate for the industry

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 55
Which is performed as part of the recommended risk management procedure?

  • A. Resolution of conflicts between the project and the programme board
  • B. Review of risk management practices to ensure that they are performed effectively
  • C. Sending of information about risks to the project to project stakeholders
  • D. Allocation of a budget to investigate issues facing the project

Answer: C

 

NEW QUESTION 56
Which activity takes place within the Managing a Stage Boundary process?

  • A. Produce an Exception Plan
  • B. Authorize a Stage Plan for the next stage
  • C. Take corrective action within the limits of a stage's tolerance
  • D. Produce Highlight Reports

Answer: A

 

NEW QUESTION 57
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

  • A. Both 1 and 2 are true
  • B. Neither 1 or 2 are true
  • C. Only 2 is true
  • D. Only 1 is true

Answer: A

 

NEW QUESTION 58
Which is a purpose of the Directing a Project process?

  • A. Ensure that work on products allocated to the team is authorized and agreed
  • B. Control the day-to-day running of the project
  • C. Create and authorize the project mandate
  • D. Delegate day-to-day management of the project to the Project Manager

Answer: D

 

NEW QUESTION 59
What must a PRINCE2 project demonstrate?

  • A. Application of PRINCE2 principles
  • B. Application of proper leadership skills
  • C. Application of the activities in each process
  • D. Application of tools appropriate for the industry

Answer: A

 

NEW QUESTION 60
How many tasks does the product-based planning technique describe?

  • A. Two
  • B. Three
  • C. One
  • D. Four

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 61
Which describes an off-specification?

  • A. A prototype demonstrating a possible design solution
  • B. The addition of an improvement to a product description
  • C. An interdependency between products that was previously unidentified
  • D. The production of more than the defined quantity of a specialist product

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/

 

NEW QUESTION 62
......

Updated PRINCE2 Study Guide PRINCE2Foundation Dumps Questions: https://www.examsreviews.com/PRINCE2Foundation-pass4sure-exam-review.html

Valid PRINCE2Foundation exam with PRINCE2 Real Exam Questions: https://drive.google.com/open?id=1vWSpOUJVBZZqlGe4F7Aod_ZgG9f1a8uI